US Navy seeks to address major programme delays caused by shipbuilding…

Aircraft carrier Enterprise is running 18–26 months behind schedule. (Janes/Michael Fabey)

Major US Navy (USN) shipbuilding programmes are running one to three years behind schedule due in a large part to the lack of a sufficient workforce and supply-chain disruptions, according to a 45-day shipbuilding review of these programmes and USN officials who spoke about the review's findings on 2 April during a roundtable media discussion.

While some of these issues are “lingering” Covid impacts, Nickolas Guertin, assistant secretary of the navy for research, development, and acquisition, acknowledged during the roundtable that they have become a new normal of the shipbuilding waterfront world.

“The supply chain is different now,” he said, adding some materials must be acquired much sooner than before.

In addition, he said, not only has there been a thinning of the workforce, there has also been a “greening of the workforce” – with veteran workers leaving the ranks and being replaced by younger and less-experienced workers, which also has an impact on waterfront work.

Waterfront woes have had an impact on USN shipbuilding contracted delivery schedules, based on current performance, according to the 45-day shipbuilding review summary released on 2 April.

Columbia-class strategic submarine lead ship District of Columbia (SSBN 826), the USN's priority shipbuilding project, is now running about 12–16 months behind the scheduled October 2027 contract delivery date.

Block IV Virginia-class attack submarines (SSNs) are running about 36 months behind schedule, while Block V Virginias are running about 24 months behind schedule.

Constellation-class guided-missile frigate lead ship Constellation (FFG 62) is running 36 months behind schedule and Ford-class aircraft carrier Enterprise (CVN 80) is running 18–26 months behind schedule.

0 Comments
휴대간편 잔향대박 세련된 남자향수 15ml 9호 5입
편안한 무봉재 햇빛 차단 골프 등산 남여공용 토시
캐주얼남방 체크남방 셔츠 남성셔츠 데일리룩 INSUM21
여성 여신스타일 웨이브 전체가발
5세대 AMD 에픽 CPU로 구동되는 오라클 클라우드
갤럭시퀀텀5 케이스 천연가죽 지갑 타임 A556
서피스 랩탑5 13.5형 지문방지 액정보호필름 2매
갤럭시북 12 종이질감 보호필름 1매
유진 200 AB 엔틱 목문 방문손잡이 욕실용
LED 비정형 망고 화장대 거울 욕실 인테리어조명거울
비키 극세화 워싱 목화솜 돌소파 패드 90 x 200
보수 무늬목 테이프 x10개 다크스프러스 리폼용 리폼
삼각받침 화분 자동물 공급 기계 10p세트 화초 꽃 물주기
스포이드병 공병 유리스포이드병 스포이드 유리
초경량 담배케이스 반자동 자석 슬림형 원터치 메탈
3M 미끄럼 방지 패드 쿠션 범폰 범폼 SJ-5017 40개입

OPP 박스 테이프 투명 폭50mmX길이80m 택배 포장 이사
칠성상회
3M 몰딩 양면테이프 회색 8mm x 11M
바이플러스

맨위로↑